POP milestones#

POP status extracted from Jira.

Download pop.csv here.

2023-12-19 17:32

Issue key

Summary

Assignee

Due Date

Component

Status

Implementation Status Description

PREOPS-3635

L2 - Production web products updated and with better than 75% uptime

Alan Strauss

2024-09-30

Education and Public Outreach

In Progress

Met with CST to continue to identify/define “For Scientists” scope.  Troubleshooting k8s release of rubinobservatory.org ahead of  A/B testing.  Continued development of Investigations v2 (targeting 12/5 for handoff to, and training of, the EPO Education Team).

PREOPS-3634

L2 - System Performance systems in place

Leanne Guy

2024-09-30

System Performance

In Progress

This is progressing and on track

PREOPS-3633

L2 - RPF readiness for DP1

Leanne Guy

2024-09-30

System Performance

In Progress

This is progressing and on track

PREOPS-3632

L2 - Deliver final Early Science Plan

Leanne Guy

2024-09-30

System Performance

In Progress

Progressing and on track

PREOPS-3631

L2 - Data Management ready for LSSTCam

Wil O’Mullane

2024-08-31

Data Management

In Progress

This is progressing for now.

PREOPS-3630

L2 - Deliver the LSST Cadence

Robert Blum

2024-09-30

Director’s Office

In Progress

The Survey Scheduling team has released baseline cadence v3.3. This includes 3xAg coating and overall major throughput gain, but decrease in u band depth per visit. The SCOC is analyzing the impact of the changes. There will be a community workshop in January to discuss this and other cadence issues remaining. The work to complete this milestone is on track.

PREOPS-3629

L2 - Establish Resource Allocation Committee (RAC)

Robert Blum

2023-12-31

Director’s Office

In Progress

No further progress to report, but this milestone is still on track.

PREOPS-3628

L2 - Establish LSST Resource Forum

Robert Blum

2024-09-30

Director’s Office

In Progress

No further progress to report, but this milestone is still on track.

PREOPS-3627

L2 - Complete the FY25 Summit Maintenance and Service Plan

Chuck Claver

2024-09-30

Observatory Operations

To Do

Not yet started.  This has been delayed due to delays in the advancement of the construction project.  This milestone was created assuming an earlier schedule plan from the construction plan which has be superseded by a revised schedule.

Propose to move this milestone to be consistent with previous assumptions but based on revised construction schedule.

There is also influence from the revisions to the Strategic Maintenance plan which has been similarly delayed.

Tue Dec 19 17:32:58 UTC 2023